Second Avenue Line

From Free net encyclopedia

Image:2nd Avenue Subway.png The Second Avenue Line, usually called the Second Avenue Subway (SAS), refers to a series of public works projects and engineering studies undertaken to construct a subway underneath Second Avenue in New York City's borough of Manhattan. A dream for more than three quarters of a century, Second Avenue has yet to see significant progress towards this goal. The SAS is often cited as a particularly egregious example of bureaucratic largesse and government ineptitude. However, the reasons for its failure thus far are varied and complex.

Contents

Information

Originally proposed in 1929 as part of the massive IND Second System, the need for the Second Avenue Subway line has grown over the years, especially in recent years, as the East Side of Manhattan has experienced significant residential development. Manhattan's Upper East Side currently does not have many transportation options. Today, the four-track IRT Lexington Avenue Line, the most crowded in the country, is the East Side's sole rapid transit option. (Its ridership exceeds that of the entire Washington Metro.) It is notorious for overcrowding, including a few newsworthy incidents of people hanging out of the subway cars and being dragged. Local bus routes are just as crowded during various times of the day. The SAS would add another two tracks to fill the gap that has existed since the elevated IRT Second Avenue Line was demolished in 1940-42 and IRT Third Avenue Line was removed in the 1950s.

New York voters approved bond acts for its construction in 1951 and in 1967. Money from the 1951 bond measure was diverted to buy new cars, lengthen platforms and maintain the aging system. The proceeds of the 1967 bond act were partly used to begin tunneling under Second Avenue. Digging began in 1972; however, a few years later, the city became insolvent. "It's the most famous thing that's never been built in New York City, so everyone is skeptical and rightly so," said Gene Russianoff, an advocate for subway riders since 1981. "It's much-promised and never delivered."

On November 8, 2005, voters in New York State passed the Transportation Bond Act, which will, among other projects, partially fund its construction. Its passage had been seen as critical to the construction of the line. In fact, the MTA chairman stated that it meant the line "will" be constructed.

History

The need for a subway line under Manhattan's Second Avenue was realized shortly after the First World War. In 1919, New York's Public Service Commission launched a study at the behest of engineer Daniel L. Turner to determine what improvements were needed in the city's mass transit system.

The Turner Plan

Turner's final paper, titled Proposed Comprehensive Rapid Transit System, was a massive plan calling for new routes under almost every north-south Manhattan avenue, extensions to lines in Brooklyn and Queens, and several crossings of The Narrows to Staten Island. Massively scaled-down versions of some of Turner's plans were found in proposals for the new city-owned Independent Subway System (IND). Among the plans for Phase II of the IND's construction, commonly called the Second System, was a massive trunk line under Second Avenue consisting of at least six tracks and numerous branches throughout Brooklyn, Queens and the Bronx.

IND Second System

In 1929, the Board of Transportation tentatively approved the IND Second System, which included a Second Avenue Line with a projected construction cost of $98,900,000, not counting land acquisition. From north to south, the 1929 plan included four tracks from the Harlem River (where it would continue north as a Bronx trunk line with several branches) to 125th Street, six tracks from 125th Street to a link with the Sixth Avenue Line at 61st Street, four tracks from 61st Street to Chambers Street, and two tracks from Chambers Street to Pine Street.

Depression

Due to the Great Depression, the soaring costs of the Second System became unmanageable. Construction on the first phase of the IND was already behind schedule, and the city and state were no longer able to provide funding. A scaled down proposal including a turnoff at 34th Street and a connection crosstown was postponed in 1931.

Further revision of the plan and more studies followed. By 1939, construction had been postponed indefinitely, and Second Avenue was relegated to "proposed" status. The 1939 plan for subway expansion took the line not only into the Bronx (by now as a single line to Throgs Neck) but also south into Brooklyn, connecting to the stub of the IND Fulton Street Line at Court Street.

The United States' entry into World War II in 1941 halted all but the most urgent public works projects, delaying the Second Avenue Line once again.

Post-war

Finally, in 1945, plans for the Second Avenue Subway were again revised. The southern two-track portion was abandoned as a possible future plan for connecting the line to Brooklyn. By 1950, the plans called for a connection from Second Avenue at 76th Street to 34th Avenue in Queens, via a new tunnel under the East River. The city was able to raise money for the construction effort—just barely—but the onset of the Korean War caused soaring prices for construction materials and saw the beginning of massive inflation.

A 1947 plan once again connected the Second Avenue Line to Brooklyn, but via the Template:BMT trackage over the Manhattan and Williamsburgh bridges. A connection would allow trains from these bridges to go onto the IND Sixth Avenue Line rather than the Second Avenue Line. Other connections to the Second Avenue Line were to be provided at 57th Street, via a line connecting to the Sixth Avenue Line; two express tracks would be built along that line north of West Fourth Street. The IRT Pelham Line would be switched to the combined Template:IND (NYCS)/Template:BMT division (this plan also includes other connections, which have been built), and connected to the Second Avenue Line. The Second Avenue Line would end just north of that connection, at 149th Street, with transfers to the IRT White Plains Road Line and the elevated IRT Third Avenue Line, the latter of which would be demolished south of 149th.

A 1954 plan added another feeder, an East River tunnel at 76th Street, connecting existing Long Island Rail Road trackage (which would be converted for subway use) to the Second Avenue Line towards downtown. This plan has been revitalized as part of the 2005 Transportation Bond Act, which would connect the LIRR trackage to Park Avenue via the 63rd Street Tunnel.

The southernmost part of the 1947 plan, connecting the two BMT bridges to the IND Sixth Avenue Line, was built in the 1960s and opened in 1967 as the Chrystie Street Connection. Other parts of that plan were carried out, including the connection at 57th Street (moved to 63rd Street) and the abandonment of the IRT Third Avenue Line south of 149th Street, but the rest of the Second Avenue Line was not built. Plans now call for an additional two tracks in the Chrystie Street area for the Second Avenue mainline; current plans have the new tracks under the old ones, while older plans had one track on each side of the Chrystie Street Connection.

1970s: Completed segments

In 1964 the Congress passed the Urban Mass Transit Act, promising federal money to fund mass transit projects in America's cities via the Urban Mass Transportation Administration. In 1967, voters approved a massive $2.5 billion Transportation Bond Issue, which provided over $600 million for New York City projects. The Second Avenue project was given top priority, and would stretch from 34th Street to The Bronx. The City secured a UMTA grant for initial construction, and a groundbreaking ceremony was held on October 27, 1972. Construction began shortly thereafter at 2nd Avenue and 113th Street.

However, the city soon experienced its most dire fiscal crisis yet. The stagnant economy of the 1970s, combined with massive outflow of city residents to the suburbs, led to fiscal disaster for the city. Construction of the subway was halted, with only three sections of tunnel having been completed, as well as the Chrystie Street Connection. These sections are between Pell and Canal, 99th and 105th, and 110th and 120th Streets. The two northern sections between 99th and 105th, and 110th and 120th Streets, will be used in Phase 2 of the current SAS plan (96th to 125th). The section from Pell to Canal will not be used under the current preferred alternative, which will bring the line a few blocks away from this section. Construction was also begun between 2nd and 9th Streets, though the extent is unknown; some rumors say that only utilities were relocated, while others say that it was excavated but filled back in.[1]

Current Developments

Beginning with the city's economic recovery in the 1990s, efforts were again made to complete construction of the SAS. Rising ridership on the Lexington Avenue Line, the only subway line east of Central Park in Manhattan, further pushed the need for the Second Avenue Subway as capacity and safety concerns rose. The current plan calls for a two-track line extending from 125th street to Hanover Square. A connection to the Broadway-BMT Line via the BMT 63rd Street Line will allow Broadway-BMT trains to use the SAS. To facilitate construction of the SAS to relieve congestion on the Lexington Avenue line, the Second Avenue line will be built and opened in sections beginning with a connection to the unused platform on the BMT 63rd Street Line's Lexington Avenue station. The Second Avenue line will then slowly extend north and south from this first section.

The MTA's final environmental impact statement was approved in April 2004. The latest proposal is for a two track line from 125th Street and Lexington Avenue in Harlem, that would connect with the 4, 5, 6 subways via a major station, which would run down 2nd Avenue to the financial district in Manhattan. The new 2nd Avenue Subway line, which may be called the "T" subway line, is proposed to be built in four segments with numerous connections to other subway lines. The first segment (phase 1) is a proposed stub line along the Upper East Side from 96th Street with a connection via the 63 Street tunnel to the Broadway line (N, R) for service downtown. The other four segments, in the order that they are proposed to be built are 125th Street to 96th Street (phase 2), 63rd Street to Houston Street (phase 3) and Houston Street to a southern Terminal at Hanover Square in far lower Manhattan (phase 4).

Because New York voters passed a transportation bond issue in November 2005, state funding is now in place for section 1 and the MTA is actively seeking a full funding agreement from the Federal Government to complete phase 1. The general consensus is that phase 2 will also be built, especially since it will take advantage of 15 blocks of subway tunnels that were built in the 1970s above 99th Street and are still in usable condition.

The lower Manhattan segments are less certain, but population pressures might force them to be built as well, especially if phases 1 & 2 are built without too many problems. The currently under construction East Side Access project, which will bring thousands of Long Island Rail Road commuters into Grand Central Station by 2012, will put even more pressure on the overburdend Lexington Avenue Line, and is certain to help push along the lower portion of the 2nd Avenue Subway line project (phases 3 and 4) as the city comes to grips with pressure for new East Side subway service.

Phase 1 is in the advanced planning stages, including engineering, and construction contracts are expected to be awarded sometime in 2006. The subway will be built with deep boring methods and avoid the cumbersome utility relocation and cut-and-cover methods of past generations that made subway building a major inconvenience. Only the stations will be cut-and-cover and efforts are underway to minimize the impacts of construction.

The Federal Transit Administration announced that it expects the first section of the project (96th St. to 63rd St.) to enter the Final Design phase on 4/18/06. This is a significant step towards obtaining the necessary federal funding to start construction.

Planned SAS Route/Stations

The plans for the Second Avenue Subway involve digging 8.5 miles of new track from 125th Street in Harlem south to the Hanover Square in the Financial District. Initially, during Phase I, the 2nd Avenue line will run from 2nd Avenue and 96th Street to the 63rd Street tunnel and join the Broadway line via a pre-existing, but unused, tunnel connection from the 63rd Street tunnel to the Broadway line for the direct trip downtown. Phase I stations will be located at 96th Street, 86th Street and 72nd Street. It is anticipated that the Q train will be extended from its current terminus at 57th Street and 7th Avenue to 125th Street and Lexington Avenue. The new stations of the Second Avenue trunk line, once all of the Phases (1-4) are built are proposed as follows:

Image:T Line Banner.jpg

Station Phase Transfers & notes
125th Street2Template:NYCS Lexington (Lexington Avenue Line/Jerome Avenue Line/Pelham Line)
connection to 125th Street (Template:MNRR)
at Lexington Avenue and 125th Street
116th Street2
106th Street2
96th Street1
86th Street1
72nd Street1
(Template:NYCS Q) splits from 2nd Avenue Line via BMT 63rd Street Line for service downtown via Broadway Line (Phase 1)
55th Street3Template:NYCS Queens 53rd (Queens Boulevard Line)
Template:NYCS Lexington local (Lexington Avenue Line) (Transfers under evaluation)
42nd Street3Template:NYCS Flushing (Flushing Line)
Template:NYCS 42nd (Times Square-Grand Central Shuttle)
Template:NYCS Lexington (Lexington Avenue Line)
connection to Grand Central Terminal (Template:MNRR) (Transfers under evaluation)
34th Street3
23rd Street3
14th Street3Template:NYCS Canarsie (Canarsie Line) (Transfer under evaluation)
Houston Street3Template:NYCS Sixth south (Sixth Avenue Line) (Transfer under evaluation)
Grand Street4Template:NYCS Chrystie express (Chrystie Street Connection)
below the Chrystie Street Connection station (Construction under evaluation)
Chatham Square4at Worth Street
Seaport4at Fulton Street
Hanover Square4at Old Slip

The above stations will serve the Second Avenue main service, terminating at 125th Street and at Hanover Square. In addition to the main service, tentatively dubbed the T, and colored light blue, a connection is planned to the Broadway-BMT Line, utilizing an existing connection via the BMT 63rd Street Line, as part of phase 1. It is likely that the Template:NYCS Q service will be extended northward from Midtown-57th Street-Seventh Avenue, curving east under Central Park on the unused portion of the BMT 63rd Street Line. The Template:NYCS Q would stop at Lexington Avenue with a cross-platform transfer to the main part of the IND 63rd Street Line (Template:NYCS 63rd IND east) before merging with the Second Avenue Line at 64th Street. Thus, residents of East Harlem and the Upper East Side will have direct mass transit service down Second Avenue to the Financial District as well as direct service down Broadway to the Financial District and across the Manhattan Bridge to Brooklyn.

An additional two-track connection is planned between the line towards Lower Manhattan (around 62nd Street) and the IND 63rd Street Line towards Queens; current plans don't call for it to be used by regular service. Provisions are also being made for an extension north under Second Avenue past 125th Street to The Bronx, and an extension south to Brooklyn. No track connection will be provided to the IND Chrystie Street Connection.

Just north of Broome Street, the subway will pass under a short unused highway tunnel, the only part of the Lower Manhattan Expressway to be built.

Construction Status

While construction has not yet begun, with the recent passage of the Transportation Bond Act, it is expected to begin soon.

  • 2012-2015: Phase 1 (96th St. to 63rd St.) State Funding In-Place, Pending Federal Funding, Construction Contracts Expected in 2006
  • 2014-2017: Phase 2 (125th St. to 96th St.) Engineering ongoing. No funding commitments.
  • 2015-2018: Phase 3 (63rd St. to Houston St.) Engineering ongoing. No funding commitments.
  • 2017-2020: Phase 4 (Houston St. to Hanover Sqr.) Engineering ongoing. No funding commitments.
  • This timeline is subject to change.

Politics

A similar public works project in New York, the $6.3 Billion LIRR East Side Access project, which will bring the Long Island Rail Road into Grand Central Terminal, has moved along rather smoothly since its inception in the late 1990s. Full funding has been provided for this public works project to complete it within the estimated 11 year timeframe, while the 2nd Avenue Subway has made virtually no progress for seven decades.

See also

External links

References

  • Subway Expansion to Cost $400,000,000 Proposed for City, New York Times December 15, 1947 page 1
New York City Subway (official site)
Services 1 2 3 4 5 6 7 A B C D E F G J L M N Q R V W Z
Shuttles (S) 42nd Street - Franklin Avenue - Rockaway Park
Unused/defunct 8 9 10 11 12 13 H K P T U X Y JFK Express
BMT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Divisions IRT - BMT - IND (Second System)
Lists Lines - Services - Stations - Terminals - Inter-division connections - Inter-division transfers - Yards
Miscellaneous Accessibility - Dual Contracts - Chaining - History - Nomenclature - Rolling stock - Straphanger
Other transit in NYC Amtrak - LIRR - Metro-North - NJ Transit - PATH - Staten Island Railway - AirTrain - Roosevelt Island Tramway